How we’re taking the smell out of the Burton plant
Our process tanks give off smelly air. We’re building a system that pulls that air off every tank, cleans it twice, and lets it out clean. The design is finished. It’s now with an independent engineer to check and sign off so it can be built.
What do you want to know?
Pick a question. Each one jumps to a short answer with a picture.
The tanks breathe out smelly air. This catches it.
Our process tanks give off air carrying sulphide gases, the rotten-egg smell. Instead of letting it drift out, every tank gets a vent that sucks that air into one pipe and sends it through two cleaning stages.
Engineering firm GHD wrote the concept design (project 12610752, Rev 1, issued 30 May 2024): pull 400 L/s off the tanks, clean it in a bioscrubber first, then polish it in a soil bed. That report is still the rulebook. It sets the limits the design has to stay inside.
Agricultural Organics took GHD’s idea and worked it up to full drawings that match how the plant is actually built and run. Same process, same 400 L/s. Anywhere we did something different is written down as a change, with the maths behind it.
The drawings are stamped “For engineer review, not for construction”. Once an Australian-registered engineer signs them, they become ready to build.
Follow the air from the tank to the sky
Seven steps. Smelly air goes in at the top, clean air comes out at the bottom. Tap “the detail” on any step for the engineering numbers.
46 vent points suck the air off the tanks so it can’t escape.
The detail
- 34 points on existing tanks and vessels (the TA, TB, TC and Bamix rows).
- 12 points on the new receival-line filtration group.
- Each point has an isolation valve, a fixed orifice plate (a plate with a set-size hole) and a pair of test ports at tank height.
- The air is shared out between tanks by measuring at those test ports, not by fiddling with valves.
A 300 mm plastic pipe, about 95 m long, carries all the air to the treatment area.
The detail
- DN300 SN8 DWV PVC-U main header: about 88 m inside the building, 7 m outside, plus a sub-main of about 10 m.
- Laid on a slope back towards the tanks, so condensation runs back rather than pooling.
- Built in 4 m solvent-welded lengths, each with a fixed point and a slip expansion coupling so it can grow and shrink with heat.
Fan FN-02 does the sucking. It keeps the pipe under suction so air is always drawn off the tanks.
A big tank packed with plastic pieces kept wet with liquid. As the air passes through, the rotten-egg gases get washed out.
The detail
- 3.8 m diameter polyethylene tank, built to our own design.
- 1.5 m of random plastic packing, with 1.0 m doing the work.
- Air spends 28 seconds in the packing (empty-bed residence time).
- The liquid is pumped round and round. It’s drawn off in batches as a process product (see Where does the water go?).
- Room, pipe tappings, a switchboard way and control inputs are left for adding liquid cooling and dosing later. They’re not fitted now.
Fan FN-01 draws air out of the scrubber and pushes it into the soil bed.
The detail
- Holds the top of the scrubber tank at −50 Pa, just a whisker below normal air pressure.
- Duty 3,963 Pa. The whole system works at 5,075 Pa.
- Those numbers went up slightly after the soil bed end walls were added on 23 Oct. The fan choice and electrical figures were updated to match.
The air is pushed up through a metre of soil media, which polishes off what’s left of the smell.
The detail
- Two cells built from Humes invert units, 53.1 m² of working area, 1.0 m of media.
- Air spends 120 seconds in the media.
- GHD’s pattern of holes in the air pipes under the bed is kept as it was.
- Watered with RO water, with mains water as a backup.
- Quarry rock packed in by excavator against the north and south walls, up to 75% of the exposed wall height. The ends are left clear.
- End walls at full leg height in concrete or masonry, with the pipe penetrations, zone valves at ground level and a DN225 air header inside each cell.
- Drains underneath are water-sealed so air can’t sneak out the bottom.
After both stages, the treated air leaves through the top of the soil bed.
Stage 1 vs stage 2 at a glance
Packing: 1.5 m (1.0 m working)
Air contact time: 28 s
Kept wet with: recirculated liquid
Area: 53.1 m²
Media depth: 1.0 m
Air contact time: 120 s
Kept wet with: RO water (mains backup)
A plastic tank can’t take pressure. So we hold it at almost zero.
A polyethylene tank is cheap and doesn’t rust, but it isn’t built to be squeezed or blown up like a balloon. Put one fan before it and one after, and the tank sits in the middle at almost normal air pressure. That’s what lets us use a plastic tank at all.
It also fixed a mistake in the original plan
GHD’s report had a fan pushing harder than its own pipework was rated for. The working design runs the whole system at about half of that.
Not a drop to the sewer
Every bit of water the system makes stays on site. It’s caught, pumped back and used again in the plant.
A second tank (TB2) was looked at and dropped. TB1 stays as drawn.
The liquid that washes the air in the bioscrubber isn’t thrown away. It’s drawn off in batches and taken into the plant as a process product, through a 25 mm camlock fill point on the bund.
It only goes to the pit if the liquid gets too salty (a high-high conductivity alarm). That’s a safety backstop, not the normal route.
Changed on 23 Oct 2026: it was going to be used to water the soil bed (change DC-42).
Kept simple on purpose
Fewer instruments and one control box means less to go wrong and less to look after.
42 changes from GHD’s plan, and why
Every difference from GHD is listed as a numbered change (DC-01 to DC-42), with the calculation and drawing behind it. Some earlier ones were replaced or dropped along the way. Only the final version is shown. They fall into four kinds.
Fermentation stopped. The old filtration group was replaced by receival lines.
GHD only gave its duct sizes as a proposal, so they were sized properly for the real layout.
A 13.5 kPa fan on 10 kPa ductwork, and the soil bed area didn’t add up.
Fixed orifice plates, flow-through tank operation, two fans, the Humes soil bed cells and the water return.
The last decisions, made 23 Oct 2026
These closed off the last design questions. Where they differ from the instruction of 22 Oct, the later one wins.
What’s in the pack the engineer gets
Eight folders. Everything traces back the same way: drawing → calculation → GHD’s original basis.
The calculations, section by section
- S1 tanks and flows
- S2 building pipework and orifices
- S2A filtration-group cases and header layout
- S3 main header
- S4 bioscrubber
- S5 soil bed and wastewater (5.8 end walls, 5.9 rock surround)
- S6 fans
- S7 controls and electrical
Every input is tagged: GHD, client-confirmed, vendor data or HOLD (only the five open items). The workbook recalculates with no errors. If a drawing and the workbook ever disagree, the workbook wins.
The 27 drawings
- 000 cover and register · 001 general notes and design basis · 001A open items
- 002, 002A process and instrument diagrams
- 003 to 007 building pipework (orifice plate detail on 004, Detail 3)
- 007A, 007B main header
- 008, 008A bioscrubber · 008B, 008C cooling options
- 009, 009A to 009D soil bed and treatment area
- 010 fans · 011, 011A controls
- 011B, 011C electrical layout and switchboard wiring (added at the engineer’s request, 23 Oct)
The drawings are generated from the workbook, so changing a number updates every sheet that uses it.
From sign-off to the first summer
Nothing in the design is waiting on us now. What’s left is supplier data, the ground (geotechnical) report and the engineer’s sign-off. Timings are our proposal and get confirmed with the engineer.
- The five open items get closed as stated.
- Supplier-dependent parts are checked against real supplier data before anything is made: the plastic tanks, filter chambers, 300 mm slip couplings, scrubber and soil bed media, Humes units and the electrical design. Any change becomes a recorded revision.
- Structural certifier
- Geotechnical (ground) input
- Electrical certificate of compliance
- Odour testing contractor
- Safety-in-design facilitator
- Anyone else the engineer thinks is needed
Things people usually ask
Tap a question to open the answer.
What’s a bioscrubber?
A tank full of plastic packing that’s kept wet with liquid pumped round and round. The smelly air rises through it and the sulphide gases are taken out into the liquid. Here it’s the first stage, and it does the heavy lifting.
What’s a soil bed?
A big, kept-damp bed of soil media that the air is pushed up through from pipes underneath. It catches what the scrubber missed. The air spends two minutes in it.
Why not just use one fan?
One fan would either suck the plastic scrubber tank in or blow it up. Two fans, one each side, hold it at almost normal air pressure (−50 Pa). That’s why a plastic tank works here.
What happens if something goes wrong?
24 automatic interlocks watch the system. A hard-wired pressure switch on the main pipe trips both fans if pressure goes outside its limits. If the scrubber liquid gets too salty, it’s dumped to the pit automatically.
Does any of it go down the drain?
No. There’s no sewer connection. All the water goes back into tank TB1 or into production.
How will you know it’s working?
Every vent has test ports, so the airflow at each tank is measured rather than guessed. After start-up, an odour testing contractor proves the results. Then the first summer is reviewed to see if cooling is needed.
When will it be built?
After the engineer signs off and the open items are closed. The longest lead item is the scrubber tank at about 7 weeks. Firm dates get set with the engineer.
A few things to fill this page out
This page is built from your cover letter only. Answer these and we’ll add them in.
- What are the five open items, in a line each?
- Who’s the reviewing engineer? The letter still has their name to be filled in.
- What started this: neighbour complaints, the EPA licence, or planning ahead?
- Is this page for neighbours and the public, for staff, or for customers? That decides how much detail stays in.
- Any photos of the tanks, the site for the soil bed, or the drawings we can show?
- Which product does the scrubber liquid go into? Worth a line if it’s a selling point.
- Rough build dates you’re happy to share?
Source: Agricultural Organics cover letter to the reviewing engineer, 23 Oct 2026, reviewing GHD Concept Design Report 12610752 Rev 1 (30 May 2024).